Bond Construction begins on October 20th, 2025

Areas in red will be for construction equipment. This will affect parking availability. Please excuse us for having fewer parking spaces due to construction.

Areas in green are Bond Projects.

+Demolition of old administration and business annex in Oct-Nov

+Band Hall expansion - November; Parking &through traffic affected.

+Gym - Dirt work begins November; Parking very limited in this area

+Tennis Courts - TBD; Parking is not allowed in this area until completion, since this is also used for construction equipment.

+HS Vestibule - May; Parking will not be affected until May 2026

+MS Vestibule - May; Parking will not be affected until May 2026

New Diana construction and parking map

NEW DIANA INDEPENDENT SCHOOL DISTRICT

BOND 2024 CONSTRUCTION TIMELINE

  • Receive Proposals

    • September 2, 2025

  • Board approves Proposals

    • September 2025

  • Demolition of Old Admin, Business Annex, Old FB Concession

    • October 2025

  • Earthwork begins on Band Hall Expansion and new Gymnasium

    • November 2025

  • Work begins on HS Offices/Classrooms & MS Vestibules

    • May 2026

  • HS Offices and MS Vestibule Completion

    • Summer 2026

  • Band Hall Expansion Completion

    • Summer 2026

  • New Gym Completion

    • Summer 2027

New Diana Independent School District. Bond 2024 Construction Timeline