Bond Construction begins on October 20th, 2025
Areas in red will be for construction equipment. This will affect parking availability. Please excuse us for having fewer parking spaces due to construction.
Areas in green are Bond Projects.
+Demolition of old administration and business annex in Oct-Nov
+Band Hall expansion - November; Parking &through traffic affected.
+Gym - Dirt work begins November; Parking very limited in this area
+Tennis Courts - TBD; Parking is not allowed in this area until completion, since this is also used for construction equipment.
+HS Vestibule - May; Parking will not be affected until May 2026
+MS Vestibule - May; Parking will not be affected until May 2026

NEW DIANA INDEPENDENT SCHOOL DISTRICT
BOND 2024 CONSTRUCTION TIMELINE
Receive Proposals
September 2, 2025
Board approves Proposals
September 2025
Demolition of Old Admin, Business Annex, Old FB Concession
October 2025
Earthwork begins on Band Hall Expansion and new Gymnasium
November 2025
Work begins on HS Offices/Classrooms & MS Vestibules
May 2026
HS Offices and MS Vestibule Completion
Summer 2026
Band Hall Expansion Completion
Summer 2026
New Gym Completion
Summer 2027